[University](https://www.pelles.ai/university) [Articles](https://www.pelles.ai/university/articles) Inclusions vs Exclusions: The Subcontractor Playbook + Templates

MEP Preconstruction Estimating Scope Management

# Inclusions vs Exclusions: The Subcontractor Playbook + Templates

A complete guide to writing clear inclusions and exclusions lists that protect your scope and prevent disputes on construction projects.

[Pelles Team AI + Construction Experts](https://www.pelles.ai/university/about)

Sep 30, 2025 6 min read

[Visual Summary · Click to jump to infographic](#visual-summary) [Interactive Games](#interactive-games)

Listen to article

The fastest way to lose money on a project: assume your scope boundaries are understood.

Your inclusions and exclusions list is your first line of defense against scope creep, GC buy-out games, and "that's in your contract" arguments. A good list doesn't just protect you—it prevents disputes before they start.

Here's how to build one that works.

## Why Inclusions and Exclusions Get Ignored

Most estimators treat inclusions/exclusions as an afterthought—copy-paste from the last bid, make a few tweaks, done.

Then reality hits:

- "We assumed you were providing the fire stopping."
- "Your bid included electrical connections, right?"
- "The spec says testing—that's your scope."

Every one of these conversations costs you money or relationship capital. Usually both.

## The Difference Between Inclusions and Exclusions

### Inclusions

What you ARE providing. Be specific enough that there's no ambiguity about what your price covers.

Good inclusion: "Installation of all ductwork shown on Sheets M-201 through M-210, including rectangular duct, round duct, flex connections, and duct accessories."

### Exclusions

What you are NOT providing. These fall into categories:

1. **Scope in the spec but not in your trade** – Items that belong to others
2. **Scope that's unclear** – Items you're specifically declining until clarified
3. **Scope you chose not to price** – Optional or alternates you're not including

Good exclusion: "Electrical connections to mechanical equipment. All equipment provided with junction box; final connection by Electrical Contractor."

## Building Your Inclusions List

### Step 1: Start With Systems

List every system you're responsible for by name.

**Example (HVAC):**

- Chilled water piping system
- Hot water heating system
- VAV air distribution system
- Kitchen exhaust system
- Building automation and controls

### Step 2: Add Equipment

Under each system, list major equipment.

**Example (Chilled Water):**

- Chilled water pumps (2)
- Air handling units (4)
- VAV terminal units (45)
- Chilled water piping and accessories

### Step 3: Define Installation Scope

What does "installation" include for you?

**Example:**

- Receiving and unloading equipment
- Setting equipment on provided housekeeping pads
- All piping connections
- Duct connections
- Startup and testing
- Commissioning support (X hours)
- Warranty per spec (1 year)

### Step 4: List Related Scope

What related scope are you including that might otherwise be ambiguous?

**Example:**

- Pipe insulation per spec
- Equipment labels and identification
- Seismic bracing per structural drawings
- TAB by certified agency (name if selected)
- Submittal preparation (X submittals)

## Building Your Exclusions List

### Category 1: By Other Trades

These items are in the project but not your scope:

**Standard exclusions (adjust per project):**

- Concrete housekeeping pads
- Roof curbs and structural supports
- Electrical power connections
- Fire stopping of penetrations
- Painting of piping (except identification)
- Drywall framing and patching
- Ceiling grid and tile
- General purpose exhaust fans in non-mechanical rooms

### Category 2: Conditional Exclusions

Scope that depends on project-specific conditions:

- "Temporary heat—by GC unless specifically negotiated"
- "Winter protection of work—unless included in project logistics"
- "Work above 12' from floor—unless lift is provided by GC"

### Category 3: Declined Scope

Items in the spec you're consciously not pricing:

- "Extended warranty beyond one year"
- "O&M training beyond 4 hours"
- "Attic stock beyond code minimum"

**Important:** If you're declining spec-required scope, you need to be explicit. Otherwise you'll be held to the spec.

## The Master Template

Use this format:

```
INCLUSIONS:

Systems:
• [System 1] - complete as shown on drawings [list sheets]
• [System 2] - complete as shown on drawings [list sheets]

Equipment:
• [Equipment type] - [quantity] per schedule on [drawing reference]

Installation includes:
• Receiving, unloading, and setting equipment
• All [trade] connections
• Startup and testing per spec
• [TAB / Commissioning support] - [X hours / by third party / etc.]
• Submittal preparation
• As-built documentation
• O&M manuals per spec
• Warranty per spec

EXCLUSIONS:

By Other Trades:
• Concrete pads and structural supports
• Electrical power wiring and connections
• Fire stopping
• Painting (except equipment and pipe identification)
• Ceiling work

Conditional:
• Premium time (available at 1.5X labor)
• Temporary heat (by GC or negotiated separately)
• Phased occupancy impacts (bid assumes continuous access)

Not Included:
• Scope identified in Addendum 2 for future phase
• Attic stock beyond code minimum
• Extended warranty beyond 1 year (available as add option)

```

## Using AI to Build Your List

After completing your scope sheet, use this prompt:

```
Based on this MEP scope, generate a comprehensive inclusions
and exclusions list.

For inclusions:
- List all systems and major equipment
- Define what installation includes
- Note any scope that might be ambiguous

For exclusions:
- List scope typically by other trades
- Identify conditional items based on project type
- Flag any spec requirements we should explicitly decline

Format as a professional bid attachment.

```

Review and customize—AI doesn't know your specific pricing decisions.

## Common Mistakes

### Mistake 1: Being Too Vague

"Ductwork installation included" doesn't define what that means. Does it include flex duct? Kitchen hood connections? Fire dampers?

### Mistake 2: Forgetting the Obvious

If you assume everyone knows electrical is by the electrician, you're wrong. Someone will argue.

### Mistake 3: Not Updating Per Project

Using the same exclusions list for a hospital and a warehouse is lazy. Project types have different scope boundaries.

### Mistake 4: Contradicting the Spec

If the spec says fire stopping is by the mechanical contractor, you can exclude it—but you need to acknowledge that you're deviating from the spec.

## What's Next

A solid inclusions/exclusions list sets you up for clean buy-out conversations. The next step is turning this into a live document that your PMs use during construction to defend scope—not just a bid attachment that gets filed and forgotten.

---

## TL;DR

- Your inclusions/exclusions list is your first line of defense against scope creep
- Inclusions should be specific: systems, equipment, and what "installation" means
- Exclusions have three categories: by other trades, conditional, and declined scope
- Build a master template but customize it for each project type
- If you're declining spec-required scope, say so explicitly—silence means compliance

### Visual Summary

 (Image: Inclusions vs Exclusions: The Subcontractor Playbook + Templates - Visual Summary)

View full size

[Download infographic](https://assets.pelles-ai.com/media/inclusions-vs-exclusions-playbook/infographic.jpg)

### Test Your Knowledge

Question 1 of 8

#### What is the primary purpose of an inclusions and exclusions list?

To make your bid look more professional

To protect against scope creep and prevent disputes

To increase your bid price

To satisfy legal requirements

Check Answer

### Interactive Learning

0/3

Match the Terms Key Concepts Categorize These

0/5

Select a term on the left, then match it with the definition on the right

Terms

Inclusions

Exclusions

Scope Creep

Conditional Exclusions

Declined Scope

Definitions

What you ARE providing in the project scope.

What you are NOT providing in the project scope.

Uncontrolled changes or continuous growth in project scope.

Scope depending on specific project conditions.

Items in spec consciously not priced.

Card 1 of 5

Why are inclusions/exclusions important?

↻Click to flip

They prevent scope creep and disputes.

Previous Next

0/6 placed

Drag each item to its correct category

Inclusions

Exclusions

Items to categorize

Installation of ductwork

Chilled water pumps

Pipe insulation

Electrical connections

Fire stopping

Concrete pads

Share:[](https://www.linkedin.com/sharing/share-offsite/?url=https%3A%2F%2Fwww.pelles.ai%2Funiversity%2Farticles%2Finclusions-vs-exclusions-playbook "Share on LinkedIn")[](https://twitter.com/intent/tweet?url=https%3A%2F%2Fwww.pelles.ai%2Funiversity%2Farticles%2Finclusions-vs-exclusions-playbook&text=Inclusions%20vs%20Exclusions%3A%20The%20Subcontractor%20Playbook%20%2B%20Templates "Share on Twitter")

[#MEP](https://www.pelles.ai/university/articles?tag=MEP) [#Preconstruction](https://www.pelles.ai/university/articles?tag=Preconstruction) [#Estimating](https://www.pelles.ai/university/articles?tag=Estimating)

### Ready to implement AI in your operations?

On Pelles.ai, MEP subcontractors build practical AI apps and agents on their own documents that save time and protect margins. No developers needed.

[Schedule a consultation](https://www.pelles.ai/contact) [Read more articles](https://www.pelles.ai/university/articles)

## Continue reading

[MEP · Scope Gaps: The Most Expensive Small Miss in Construction · Understand how scope gaps form between trades and learn to identify and prevent them before they become costly disputes. · 6 min read](https://www.pelles.ai/university/articles/scope-gaps-expensive-miss) [MEP · How to Track Scope Creep Before It Hits Your Profit · Identify and document scope creep as it happens so you can recover costs or stop the bleeding before project margins disappear. · 6 min read](https://www.pelles.ai/university/articles/track-scope-creep-before-profit-hit) [MEP · The 10-Minute Bid Package Triage Using AI · Learn how to quickly assess bid packages and decide which opportunities are worth your team's time using a structured AI-assisted triage process. · 5 min read](https://www.pelles.ai/university/articles/10-minute-bid-package-triage)